An EV charger permit in Brentwood, TN is a state electrical permit, not a city one. The City of Brentwood codes office handles building permits. Electrical permits and inspections come from the State of Tennessee through its CORE online system. Your licensed electrician buys the permit and requests the state inspection.

Last checked:

Who Is This For?

  • Brentwood owners who want to know which office handles a charger permit
  • Anyone checking that a charger install was permitted and inspected
  • Buyers and sellers who need proof of permitted electrical work
  • Owners comparing the license held by different electricians

What Is Included?

  • A state electrical permit bought by your electrician through CORE
  • An inspection request filed with the state
  • A field inspection by a state Deputy Electrical Inspector
  • Fixes for any items the inspector flags, then a follow-up visit
  • A record of the permit that you can keep with your home files

Process

How Does the Process Work?

  1. Call and Describe Your Setup

    Share your address, your panel, and the charger you plan to use. Your address decides which office handles the permit.

  2. Written Quote

    Your electrician looks at the home and gives a written quote. Ask that it lists the permit.

  3. State Permit Through CORE

    Your electrician buys the state electrical permit online at core.tn.gov before the work starts.

  4. Install and Request the Inspection

    Once the wiring is done, your electrician requests the inspection through CORE.

  5. State Inspection

    A contracted Deputy Electrical Inspector checks the work in the field. Any flagged items get fixed and checked again.

Cost

What Affects the Cost?

Permit fees are set by the state and the issuing office, and there is no verified range to print. Your written quote should show whether the permit is included.

Size of the Job

A single charger circuit and a full service change are permitted at different levels.

Which Office Has the Job

Addresses outside Brentwood may fall under a city or Metro program with its own fees.

Follow-Up Visits

Items that fail inspection need a fix and a second visit, which can add cost.

Panel or Service Work

If the job includes a new panel, the utility may also need to be involved.

Call to speak with a local electrician about your EV charger install.

Call (615) 235-9332
As of October 2026

Which Rules Apply to a Brentwood Charger Permit?

Tennessee enforces the 2017 NEC, as of October 2026, under Rule Chapter 0780-02-01. NEC Article 625 covers EV charging equipment. Section 625.40 calls for an individual branch circuit for each EV outlet, and 625.41 sizes the breaker at 125% of the charger's maximum load. A load calculation under Article 220 shows whether the panel has room.

Rule 0780-02-01-.17 says no local government may adopt or enforce electrical standards that are less stringent than the state's. Cities that run their own programs can add rules, but they cannot set a lower bar.

GFCI protection is expected on a receptacle used for EV charging. Your electrician confirms the inspector's exact requirements. The state notes that the licensee doing the work gets the permit, not the property owner, so a licensed electrician should be on the permit.

Why Does the State Handle Electrical Permits in Brentwood?

The City of Brentwood codes office handles building permits under its adopted codes. For wiring, the city's own FAQ points to the state. All electrical and low voltage permits and inspections in Brentwood go through the State of Tennessee Electrical Permit Department, part of the State Fire Marshal's Office.

Here is how CORE works for a reader. The licensee buys the permit online at core.tn.gov and requests the inspection there. A contracted Deputy Electrical Inspector then comes to check the work. There are about 100 of these inspectors statewide, so your electrician sets the visit with the state.

Nearby areas differ. Franklin and Spring Hill run their own electrical programs inside city limits. Oak Hill and Forest Hills sit in Davidson County, where Metro Nashville Codes handles electrical permits. Nolensville uses the state program, much like Brentwood.

What License Should Your Electrician Hold?

Tennessee has two paths. A Limited Licensed Electrician (LLE) holds an individual license for projects under $25,000, counting both materials and labor. An LLE may not use the title contractor, and a project may not be split into phases to stay under the limit.

For projects of $25,000 and up, the state requires a contractor license with a CE (electrical) classification. A CE contractor license is accepted statewide. Tennessee has no reciprocity with other states, so an out-of-state license does not count here. Some local agencies do not accept the LLE, which matters for jobs in cities with their own programs.

You can check any license on the state's public license lookup. Ask your electrician for the license number and search it before work starts. For a home charger, an LLE or an electrical contractor can both do the job if the project is under $25,000.

How Do You Find Your Permit Authority?

A Brentwood mailing address does not always mean Brentwood city limits. Use these steps to find out which office handles your permit:

  • Check whether the property is inside city limits on your property tax bill.
  • Then go to that city's website and look for its codes or building department.
  • Look for a line on who handles electrical permits. Some cities, like Brentwood, point to the state.
  • If the city points to the state, the permit goes through CORE at core.tn.gov.
  • If your address is in Davidson County, Metro Nashville Codes handles electrical permits.
  • Still unsure? Ask your electrician to confirm before the quote is final.

Permits and Inspections FAQs

Do I Need a Permit for an EV Charger in Brentwood, TN?

Yes, you need a state electrical permit for a new charger circuit. In Brentwood, electrical permits and inspections come from the State of Tennessee, not the city. Your electrician buys the permit through CORE. The FAQ page has more on permits.

Who Buys the Electrical Permit?

Your licensed electrician buys it. The state notes that the licensee doing the work obtains the permit, not the property owner. Ask that the permit is listed on your written quote.

Who Inspects the Work?

A contracted state Deputy Electrical Inspector checks the work in Brentwood. Your electrician requests the visit through CORE once the wiring is done. If anything fails, it gets fixed and checked again.

What Is the Difference Between an LLE and a Contractor?

An LLE is an individual license for projects under $25,000. Projects of $25,000 and up need a state license with a CE (electrical) classification. That CE license belongs to an electrical contractor, and both show up on the state's public license lookup.

Does Franklin Handle Permits the Same Way?

No, Franklin runs its own electrical program inside city limits. Spring Hill does too, and Metro Nashville Codes covers Oak Hill and Forest Hills. See the Franklin page for its local details.

Can a Permit Affect My Rebate?

Some programs ask for a receipt, and a permitted job keeps your records clean. Middle Tennessee Electric's EV Ready credit asks for a receipt with the online form. See rebates and incentives for current programs.

Keep Reading

Get Connected Today

Call to speak with a local electrician about your EV charger install.

Installs are performed by independent electricians licensed in Tennessee.

Call (615) 235-9332
Get connected today(615) 235-9332